The Inquiry opened at 10 am on Tuesday 21 January 2025 and closed on Wednesday 29 January.
The final version of the Inquiry Documents List is Inquiry Documents List 31 1 2025
29 January 2025
The Closing Submissions on behalf of the applicant have been submitted to the Inquiry Closing Submissions for the Applicant – 29 Jan 2025
29 January 2025
The Closing Submissions on behalf of the Consortium have been submitted to the Inquiry
29 January 2025
The following documents have this morning been submitted by the applicant –
28 January 2025
The Inquiry Documents List has been further updated, the new documents are highlighted on Inquiry Documents List 28 1 2025 rev2
28 January 2025
The Inquiry Documents List has been further updated, the new documents are highlighted on Inquiry Documents List 28 1 2025 rev1
28 January 2025
The Inquiry Documents List has been updated, the new documents are highlighted on Inquiry Documents List 28 1 2025
27 January 2025
The Inquiry Documents List has been updated, the new documents are highlighted on Inquiry Documents List 27 1 2025
24 January 2025
The following documents have been submitted by the applicant –
Statutory Instrument draft 231.25
21 January 2025
The following Bundles of all the Core Documents and Evidence have been prepared by the applicant and will be referred to in the inquiry Bundle/Page number –
Bundle 1 – CDA – Revised Application Documents
Bundle 2 – CDB – Legislation Previous Inquiry Documents
Bundle 3 – App – Ferry Company (reduced)
Bundle 4 – OBJ – Objector’s Bundle (new)
21 January 2025
The opening statement of the Ferry Company is now available Ferry Company Opening Submissions – 21 January 2025
The opening statement of the Consortium is now available Bournemouth-Swanage Ferry v Swanage Town Council v others opening 250121
20 January 2025
PLEASE NOTE THAT THE ORDER OF THE FERRY COMPANY’S WITNESSES HAS CHANGED – Inquiry Programme 20 1 2025
17 January 2025
16 January 2025
SOCG/2 has been added to Inquiry Documents List 16 1 2025
14 January 2025
A Statement of Common Ground between the Ferry Company and the Consortium has been submitted to the Inquiry Statement of Common Gound Ferry Company-Consortium_
14 January 2025
The Inquiry Programme is now available Inquiry Programme 14 1 2025
14 January 2025
The Inquiry Documents List has been updated, the new document is highlighted on Inquiry Documents List 14 1 2025
9 January 2025
CDB.9 has been added to CD List 9 1 2025
7 January 2025
CDB.8 has been added to CD List 7 1 2025
3 January 2025
The rebuttal evidence submitted today is highlighted on Inquiry Documents List 3 1 2025
19 December 2024
The Inquiry Documents List has been updated to include statements submitted by the third-parties Inquiry Documents List 19 12 24
13 December 2014
The Inspector has issued a Pre-Inquiry Note Pre-Inquiry Note
12 December 2024
The evidence of the Consortium and some further third-party statements have been added to Inquiry Documents List 12 12 24
12 December 2024
All the submitted objections are now available to view, please note that for individuals the objections have been redacted and anonymised Objections received to the Toll Review Application
3 December 2024
CDA.6A, CDA.6B and CDB.7 have been added to CD List 3 12 2024
25 November 2024
The Core Documents List has been updated CD List 25 11 2024
22 November 2024
The Core Documents List is now available CD List 22 11 2024
The Inquiry Documents List is now available Inquiry Documents List 22 11 24
18 November 2024
The applicant has submitted appendices A and C of Mr Thomas’ evidence in Excel spreadsheet format including the formulae
Copy of Statement of Kevin Thomas Appendix A – with formulae
Copy of Statement of Kevin Thomas Appendix C – with formulae
11 November 2024
The applicant has submitted appendices A and C of Mr Thomas’ evidence in Excel spreadsheet format
Copy of Statement of Kevin Thomas Appendix A
Copy of Statement of Kevin Thomas Appendix C
7 November 2024
The applicant has today submitted their evidence to the Inquiry
Statement of Michael Kean 7.11.24 (as served)
Appendices to the Financial Statement and Response of Michael Kean
Statement of Kevin Thomas 7.11.24 (as served)
Appendices to the Financial Statement and Response of Kevin Thomas
The Inspector for the Inquiry was Kevin Gleeson BA MCD MRTPI
The final version of the List is CD List 9 1 2025
Comments are closed.